How to estimate in-place concrete strength from temperature logs with the maturity method, with a cold-weather pour that takes six days to reach 3,000 psi

The maturity method turns hourly concrete temperatures into a strength estimate that can time form stripping, reshoring and the end of winter protection.

2,820 156 · +6.8% on the period · +803.8% on the year

The example slab passes the 2,693 °C-hour target at about hour 148

Cumulative temperature-time factor, °C-hours above a -10°C datum, by hours after placement. Example calculation.

The example slab passes the 2,693 °C-hour target at about hour 148Line chart with 13 points from 12 to 156. Series: Cumulative TTF (C-hours). Values range from 312 to 2,820.01,0002,0003,00012488412015612: 31224: 61236: 86448: 1,09260: 1,30872: 1,51284: 1,71696: 1,908108: 2,100120: 2,280132: 2,460144: 2,640156: 2,8202,820
The example slab passes the 2,693 °C-hour target at about hour 148Line chart with 13 points from 12 to 156. Series: Cumulative TTF (C-hours). Values range from 312 to 2,820.01,0002,0003,000128415612: 31224: 61236: 86448: 1,09260: 1,30872: 1,51284: 1,71696: 1,908108: 2,100120: 2,280132: 2,460144: 2,640156: 2,8202,820
Hypothetical cold-weather pour, 12-hour average concrete temperatures. Source: ia.iowadot.gov
DateTrendCategoryTitleSummary
DataHow to estimate in-place concrete strength from temperature logs with the maturity method, with a cold-weather pour that takes six days to reach 3,000 psiThe maturity method turns hourly concrete temperatures into a strength estimate that can time form stripping, reshoring and the end of winter protection.