Data
How to price force account work with DOT markups, where $10,400 of cost bills as $12,680 under Iowa's rules
Iowa DOT adds 35% to force account labor, 10% to payroll taxes and 15% to materials, so $10,400 of cost bills as $12,680.
Tag
Data
A measured mile compares a crew's unimpacted and impacted unit rates on the same job. This example turns 12 weeks of conduit data into 960 lost hours.
0.12 12 · +5.1% on the period
Hours per foot rose after the week 4 redesign and stayed above the measured mile
Labor hours per linear foot of conduit, example crew, weeks 1 to 12
Data
Iowa DOT adds 35% to force account labor, 10% to payroll taxes and 15% to materials, so $10,400 of cost bills as $12,680.
Data
NOAA climate normals count rain days by month at more than 15,000 stations. This example turns Chicago O'Hare's counts into a work-day weather allowance.
Feature Data
A fuel price adjustment pays for estimated gallons at the change in a diesel index. This example prices 160,000 cubic yards of earthwork.
Data
A worked example of the Corps of Engineers equipment rate method prices a $400,000 excavator at $93.99 an hour and $21.59 on standby.
Data
An escalation clause moves a fixed price with a named BLS index. This example adjusts $1.2 million of steel with a 3% trigger and a 10% cap.
Data
Change order rate divides approved change orders by the original contract. This example splits it by job and by cause across six jobs.
| Date | Trend | Category | Title | Summary |
|---|---|---|---|---|
| Data | How to price force account work with DOT markups, where $10,400 of cost bills as $12,680 under Iowa's rules | Iowa DOT adds 35% to force account labor, 10% to payroll taxes and 15% to materials, so $10,400 of cost bills as $12,680. | ||
| Data | How to compute lost labor hours with a measured mile, worked through a 12-week conduit example | A measured mile compares a crew's unimpacted and impacted unit rates on the same job. This example turns 12 weeks of conduit data into 960 lost hours. | ||
| Data | How to set monthly weather delay days from NOAA climate normals, with a Chicago O'Hare example | NOAA climate normals count rain days by month at more than 15,000 stations. This example turns Chicago O'Hare's counts into a work-day weather allowance. | ||
| Data | How to tie a fuel price adjustment to EIA diesel prices, with a 160,000-cubic-yard earthwork example Feature | A fuel price adjustment pays for estimated gallons at the change in a diesel index. This example prices 160,000 cubic yards of earthwork. | ||
| Data | How to compute an hourly rate for owned equipment with the Corps of Engineers method, with a $400,000 excavator example | A worked example of the Corps of Engineers equipment rate method prices a $400,000 excavator at $93.99 an hour and $21.59 on standby. | ||
| Data | How to tie a steel escalation clause to a BLS producer price index, with a $1.2 million example | An escalation clause moves a fixed price with a named BLS index. This example adjusts $1.2 million of steel with a 3% trigger and a 10% cap. | ||
| Data | How to measure change orders as a percent of original contract by cause, with a $100 million example | Change order rate divides approved change orders by the original contract. This example splits it by job and by cause across six jobs. |