How to compute lost labor hours with a measured mile, worked through a 12-week conduit example

A measured mile compares a crew's unimpacted and impacted unit rates on the same job. This example turns 12 weeks of conduit data into 960 lost hours.

0.12 12 · +5.1% on the period

Hours per foot rose after the week 4 redesign and stayed above the measured mile

Labor hours per linear foot of conduit, example crew, weeks 1 to 12

Hours per foot rose after the week 4 redesign and stayed above the measured mileLine chart with 12 points from 1 to 12. Series: Hours per LF, Measured mile rate, Estimate. Values range from 0.10 to 0.15.0.080.100.120.140.1613579121: 0.112: 0.103: 0.104: 0.105: 0.146: 0.157: 0.148: 0.139: 0.1310: 0.1211: 0.1212: 0.120.12Hours per LF1: 0.102: 0.103: 0.104: 0.105: 0.106: 0.107: 0.108: 0.109: 0.1010: 0.1011: 0.1012: 0.10Measured mile rate1: 0.112: 0.113: 0.114: 0.115: 0.116: 0.117: 0.118: 0.119: 0.1110: 0.1111: 0.1112: 0.11Estimate
Hours per foot rose after the week 4 redesign and stayed above the measured mileLine chart with 12 points from 1 to 12. Series: Hours per LF, Measured mile rate, Estimate. Values range from 0.10 to 0.15.0.080.10.120.140.1617121: 0.112: 0.103: 0.104: 0.105: 0.146: 0.157: 0.148: 0.139: 0.1310: 0.1211: 0.1212: 0.120.12Hours per LF1: 0.102: 0.103: 0.104: 0.105: 0.106: 0.107: 0.108: 0.109: 0.1010: 0.1011: 0.1012: 0.10Measured mile rate1: 0.112: 0.113: 0.114: 0.115: 0.116: 0.117: 0.118: 0.119: 0.1110: 0.1111: 0.1112: 0.11Estimate
Example figures. Lower is better. The measured mile is the weeks 1 to 4 average.
DateTrendCategoryTitleSummary
DataHow to price force account work with DOT markups, where $10,400 of cost bills as $12,680 under Iowa's rulesIowa DOT adds 35% to force account labor, 10% to payroll taxes and 15% to materials, so $10,400 of cost bills as $12,680.
DataHow to compute lost labor hours with a measured mile, worked through a 12-week conduit exampleA measured mile compares a crew's unimpacted and impacted unit rates on the same job. This example turns 12 weeks of conduit data into 960 lost hours.
DataHow to set monthly weather delay days from NOAA climate normals, with a Chicago O'Hare exampleNOAA climate normals count rain days by month at more than 15,000 stations. This example turns Chicago O'Hare's counts into a work-day weather allowance.
DataHow to tie a fuel price adjustment to EIA diesel prices, with a 160,000-cubic-yard earthwork example FeatureA fuel price adjustment pays for estimated gallons at the change in a diesel index. This example prices 160,000 cubic yards of earthwork.
DataHow to compute an hourly rate for owned equipment with the Corps of Engineers method, with a $400,000 excavator exampleA worked example of the Corps of Engineers equipment rate method prices a $400,000 excavator at $93.99 an hour and $21.59 on standby.
DataHow to tie a steel escalation clause to a BLS producer price index, with a $1.2 million exampleAn escalation clause moves a fixed price with a named BLS index. This example adjusts $1.2 million of steel with a 3% trigger and a 10% cap.
DataHow to measure change orders as a percent of original contract by cause, with a $100 million exampleChange order rate divides approved change orders by the original contract. This example splits it by job and by cause across six jobs.