How to compute lost labor hours with a measured mile, worked through a 12-week conduit example

A measured mile compares a crew's unimpacted and impacted unit rates on the same job. This example turns 12 weeks of conduit data into 960 lost hours.

0.12 12 · +5.1% on the period

Hours per foot rose after the week 4 redesign and stayed above the measured mile

Labor hours per linear foot of conduit, example crew, weeks 1 to 12

Hours per foot rose after the week 4 redesign and stayed above the measured mileLine chart with 12 points from 1 to 12. Series: Hours per LF, Measured mile rate, Estimate. Values range from 0.10 to 0.15.0.080.100.120.140.1613579121: 0.112: 0.103: 0.104: 0.105: 0.146: 0.157: 0.148: 0.139: 0.1310: 0.1211: 0.1212: 0.120.12Hours per LF1: 0.102: 0.103: 0.104: 0.105: 0.106: 0.107: 0.108: 0.109: 0.1010: 0.1011: 0.1012: 0.10Measured mile rate1: 0.112: 0.113: 0.114: 0.115: 0.116: 0.117: 0.118: 0.119: 0.1110: 0.1111: 0.1112: 0.11Estimate
Hours per foot rose after the week 4 redesign and stayed above the measured mileLine chart with 12 points from 1 to 12. Series: Hours per LF, Measured mile rate, Estimate. Values range from 0.10 to 0.15.0.080.10.120.140.1617121: 0.112: 0.103: 0.104: 0.105: 0.146: 0.157: 0.148: 0.139: 0.1310: 0.1211: 0.1212: 0.120.12Hours per LF1: 0.102: 0.103: 0.104: 0.105: 0.106: 0.107: 0.108: 0.109: 0.1010: 0.1011: 0.1012: 0.10Measured mile rate1: 0.112: 0.113: 0.114: 0.115: 0.116: 0.117: 0.118: 0.119: 0.1110: 0.1111: 0.1112: 0.11Estimate
Example figures. Lower is better. The measured mile is the weeks 1 to 4 average.
DateTrendCategoryTitleSummary
DataHow to compute lost labor hours with a measured mile, worked through a 12-week conduit exampleA measured mile compares a crew's unimpacted and impacted unit rates on the same job. This example turns 12 weeks of conduit data into 960 lost hours.
DataConstruction input prices held flat in October as diesel fell 4.6% and steel rose 2.7%BLS producer prices for goods bought by construction were flat in October 2026 and stand 11.5% above a year earlier, with steel up and diesel down.
DataHow to set a winter shift start from Naval Observatory twilight times and OSHA's lighting minimums, with a Detroit exampleNaval Observatory twilight times show how much of a winter shift falls in darkness, where OSHA's lighting minimums call for temporary light.
DataHow to compute working capital the way a surety does, with a $1.3 million bonding exampleSureties size a bond program from adjusted working capital. This example adjusts a $2.0 million balance to $1.3 million and converts it to capacity.
DataABC's Construction Backlog Indicator fell to 8.1 months in October as backlog for contractors without data center work dropped to 7.6 FeatureABC's backlog indicator fell 0.6 months to 8.1 in October, as firms without data center work dropped to 7.6 months and those with it rose to 11.5.
DataHow to adjust construction spending for inflation, which turns September's 2.3% nonresidential gain into a 3.0% declineDividing Census spending by a BLS construction price index separates price from volume, for national data and for your own revenue and backlog.
DataHow to budget temporary heat from heating degree days, with a Midwest example that burns 20,000 gallons of propaneHeating degree days, an enclosure's heat-loss rate and EIA propane prices turn winter temporary heat into a monthly fuel budget.
DataDodge Momentum Index fell 9.0% in October to 260.4 as commercial planning dropped 13.4%The Dodge Momentum Index fell 9.0% in October to 260.4, its first year-over-year decline in 13 releases, as data center and warehouse planning slowed.
DataConstruction employment slipped by 3,000 in October as residential specialty trade contractors cut 15,200 jobsBLS says construction employment fell by 3,000 to 8,367,000 in October 2026 as residential specialty trade contractors cut 15,200 jobs.
DataHow to weigh crew hours by BLS fatal injury rates, from roofers at 48.7 to electricians at 5.3 FeatureBLS fatal injury rates by trade turn a contractor's hours by occupation into a blended rate that shows which crews carry its fatality exposure.
DataHow to plan winter crew hours from wind chill and the ACGIH warm-up schedule, with a steel erection exampleThe NWS wind chill formula and the ACGIH work/warm-up schedule turn a cold-day forecast into break minutes and crew hours a contractor can budget.
DataConstruction job openings rose 14% to 298,000 in September as quits reached 198,000, the most in 25 monthsBLS says construction job openings rose to 298,000 in September 2026 from a revised 262,000 in August, and quits rose to 198,000.
DataConstruction spending fell 1.9% in September as residential improvement spending droppedCensus puts September 2026 construction spending at $2,186.1 billion SAAR, down 1.9% from a revised August, as private residential fell 5.5%.
DataHow to adjust a crew wage rate to another metro with BLS OEWS data, from $26 in Houston to $42 in ChicagoBLS OEWS wages let an estimator scale a home-market crew rate to another metro. In this example a $26 Houston carpenter rate becomes $42 to $45 in Chicago.
DataConstruction unemployment was 3.5% in September, and ABC's state estimates run from 1.7% in Maryland to 9.5% in North Dakota FeatureBLS put September construction unemployment at 3.5%, and ABC's state estimates range from 1.7% in Maryland to 9.5% in North Dakota.
DataHow to compute average annual receipts for the SBA size standard, with a $45 million general contractor exampleSBA averages five years of receipts, subcontractor costs included, to decide if a contractor is small. This example tracks a GC near the $45 million line.
DataConstruction employment rose in 180 of 360 metro areas in the year to September 2026, with Baton Rouge up 27%AGC's ranking of BLS metro data shows construction jobs up in 180 of 360 areas and down in 118 from September 2025 to September 2026.
DataHow to compute unabsorbed home office overhead with the Eichleay formula, with a 60-day suspension exampleThe Eichleay formula prices home office overhead lost during a federal suspension. This example turns a 60-day suspension into a $2,000 daily rate.
DataHow to set monthly weather delay days from NOAA climate normals, with a Chicago O'Hare exampleNOAA climate normals count rain days by month at more than 15,000 stations. This example turns Chicago O'Hare's counts into a work-day weather allowance.
DataHow to tie a fuel price adjustment to EIA diesel prices, with a 160,000-cubic-yard earthwork example FeatureA fuel price adjustment pays for estimated gallons at the change in a diesel index. This example prices 160,000 cubic yards of earthwork.
DataHow to price delay cost from the liquidated damages daily rate and your own field overheadFAR and FHWA rules set liquidated damages from the owner's daily costs. This example adds a contractor's field overhead and tests Saturday shifts.
DataHow to price crew vehicle mileage with the IRS rate, which rose to 76 cents a mile in JulyThe IRS business mileage rate is 76 cents for July through December 2026. This example prices a diesel crew truck's miles against $6.29 fuel.
DataHow to price per diem for a traveling crew with the FY 2027 GSA rates, $181 a day in most of the USGSA's FY 2027 standard per diem is $113 for lodging and $68 for meals. This example prices a four-person crew on a three-week out-of-town job.
DataHow to compute Prompt Payment Act interest on a late federal pay application, with a $6,740 exampleFederal agencies owe interest on late construction payments. This example computes it for two pay apps and a retainage release at the 4.75% rate.
DataArchitecture billings index fell to 44.7 in September, the lowest reading since MayThe AIA/Deltek Architecture Billings Index fell to 44.7 in September from 47.2 in August, as design contracts dropped and inquiries rose.
DataHousing starts fell 5.2% in September to 1,221,000, the second-lowest rate in 25 months FeatureCensus says September housing starts fell 5.2% to a 1,221,000 annual rate, with starts in five-plus-unit buildings down 25.9% from a year earlier.
DataHow to compute overtime premium on a 50-hour week, with a $40 wage that averages $44Overtime premium is the extra half-rate on hours past 40. This example turns a $40 wage into $44 per hour worked on a 50-hour week.
DataHow to annualize Davis-Bacon fringe benefit credit, with a $1,200 health premium worth $7.50 an hourDavis-Bacon fringe credit divides benefit cost by all hours worked. In this example a $1,200 monthly health premium earns $7.50 an hour of credit.
DataHow to compute an hourly rate for owned equipment with the Corps of Engineers method, with a $400,000 excavator exampleA worked example of the Corps of Engineers equipment rate method prices a $400,000 excavator at $93.99 an hour and $21.59 on standby.
DataHow to compute labor burden per hour worked, with a $50 wage that costs $70.86Labor burden adds payroll taxes, insurance and benefits to wages. This example turns a $50 wage into $70.86 per hour worked and checks it against BLS.
DataPrices of goods bought by construction rose 2.2% in September, led by a 24% jump in diesel FeatureBLS producer prices for goods bought by construction rose 2.2% in September and 11.2% in a year. Nonresidential building prices rose 5.4% in a year.
DataHow to tie a steel escalation clause to a BLS producer price index, with a $1.2 million exampleAn escalation clause moves a fixed price with a named BLS index. This example adjusts $1.2 million of steel with a 3% trigger and a 10% cap.
DataABC's Construction Backlog Indicator rose to 8.7 months in September, its second monthly gainABC's Construction Backlog Indicator rose 0.2 months to 8.7 months in September, with commercial and institutional backlog at 9.0 months.
DataHow to track total float across monthly schedule updates, with a 30-day exampleLogging total float on the two most critical paths at each schedule update shows how fast a job uses its cushion. This example tracks eight updates.
DataHow to adjust days sales outstanding for retainage and billing cycles, with a 51.6-day exampleA contractor's DSO mixes retainage, bills not yet due and bills past due. This example splits a 51.6-day DSO into those pieces by owner.
DataHow to track retainage aging by job and by owner, with a $1.35 million example FeatureRetainage aging starts when the release comes due. This example sorts $1.35 million of retainage on six jobs by job, by owner and by days past due.
DataHow to compute your experience mod from the NCCI worksheet, with a $100,000 loss exampleNCCI's experience mod weights claim count above claim size. This example shows ten $10,000 claims pushing a mod above 1.00 where one $100,000 claim does not.
DataHow to compute TRIR and DART from your OSHA 300 log, with a drywall contractor exampleTRIR and DART divide recordable cases by hours worked. This example computes both for a drywall contractor and compares them to BLS 2024 rates.
DataCommercial furniture prices rose 3.9% in the year to August as steel rose 23% FeatureBLS says producer prices for commercial furniture hit a record in August 2026, up 3.9% in a year, as steel mill products rose 23.4%.
DataDodge Momentum Index rose 2.4% in September to 288.0 as institutional planning grew 9.4%The Dodge Momentum Index rose 2.4% in September to 288.0, with institutional planning up 9.4% and commercial planning down 1.3%.
DataHow to track job hazard analyses as a leading safety indicatorEach signed JHA records a task, a crew and a risk score. Counted weekly, JHA coverage and crew participation show safety gaps before an injury.
DataHow to measure labor productivity from daily logs and timecards, with a drywall exampleUnits installed per labor hour come from the daily log and the timecards. This example tracks a drywall crew for 10 days against its estimate.
DataHow to compute SPI and CPI from pay application data, with a $12 million example FeatureSPI and CPI compare earned value from the pay application to the baseline plan and to job cost. This example works both for a 12-month job at month six.
DataHow to measure change orders as a percent of original contract by cause, with a $100 million exampleChange order rate divides approved change orders by the original contract. This example splits it by job and by cause across six jobs.
DataHow to track bid-hit ratio by client type, job size and estimator, with a 120-bid exampleBid-hit ratio counts bids per job won. This example splits it by client type, job size and estimator, in counts and in dollars.
DataConstruction added 11,000 jobs in September, led by nonresidential specialty trade contractorsBLS says construction employment rose by 11,000 to 8,364,000 in September 2026, led by nonresidential specialty trade contractors.
DataConstruction spending rose 0.9% in August after Census revised July up $27 billionCensus says US construction spending ran at $2,203.1 billion SAAR in August 2026, up 0.9% from a July figure revised up by 1.2%.
DataConstruction jobs rose in 177 of 360 metro areas from August 2025 to August 2026, led by Houston and Baton RougeAGC's ranking of BLS metro data shows construction jobs up in 177 of 360 areas and down in 126 from August 2025 to August 2026.
DataConstruction job openings fell 16% to 251,000 in August after BLS cut July to 299,000BLS says construction job openings fell to 251,000 in August 2026 from a revised 299,000 in July, as hires and layoffs also fell.
DataHow to compute backlog in months and compare it with ABC's 8.5-month August readingBacklog in months divides signed, unearned work by annual revenue. Here is the formula ABC uses, a worked example, and how to read yours against its survey.