When a state DOT opens bids, its tabulation often lists the engineer’s estimate next to every bidder’s total. The Federal Highway Administration (FHWA) tells state transportation agencies to track one ratio from that sheet, the difference between the bid and the engineer’s estimate divided by the estimate, and a contractor can log the same ratio on every public job it bids.

What FHWA measures

FHWA’s guidelines on the engineer’s estimate, dated October 7, 2021, are non-binding guidance for state transportation agencies. They ask agencies to monitor how reliable their estimates are and to revise their methods when market conditions change.

Earlier editions set a specific target: the engineer’s estimate within plus or minus 10 percent of the low bid on at least half of projects. The 2021 version describes that test as a past recommendation. It says that an agency choosing a 10 percent threshold should use the engineer’s estimate as the divisor. In formula terms:

  1. Variance = (bid minus engineer’s estimate) divided by engineer’s estimate.
  2. A low bid at 96% of the estimate has a variance of minus 4%.
  3. A low bid at 112% of the estimate has a variance of plus 12%.

A $1,120,000 low bid on a $1,000,000 estimate is 12% over when you divide by the estimate and 10.7% when you divide by the bid, so it fails a 10% test one way and passes it the other.

The guidance also lists the other numbers FHWA wants agencies to track for each letting: the number of bidders, the gap between the low bid and the other bids, and the spread of all bids. Its review guide asks agencies to plot how many low bids fall above and below the estimate and to count projects that drew zero, one, two, three or more bids.

Reading one bid tab

Oklahoma DOT’s bid opening report from March 12, 2026, includes an 8.57-mile asphalt resurfacing of I-35 in Norman, Cleveland County. ODOT prints each bid as a percentage of the engineer’s estimate.

I-35 resurfacing, Cleveland County, Oklahoma, Call Order 305. Bids opened March 12, 2026.
BidderTotal bidPercent of engineer's estimate
Engineer's estimate$6,040,409.18100.00%
Haskell Lemon Group (low bid)$5,844,594.9896.76%
Silver Star Construction Company$6,278,389.45103.94%
T.J. Campbell Construction Company$7,351,508.21121.71%
Overland Corporation$7,653,304.60126.70%
Source: oklahoma.gov

Four numbers come out of this sheet:

  1. The low bid was 96.76% of the estimate, a variance of minus 3.24%. It passes the 10% test.
  2. The second bid was $433,794.47 above the low bid, 7.42% of the low bid. The winner could have bid that much more and still been low.
  3. The high bid was 30.9% above the low bid.
  4. The four bids averaged 112.28% of the estimate.

The two lowest bids fell within 4% of the estimate, and the other two came in more than 20% above it. The guidance lists the distribution of bids among the factors an agency weighs before it awards.

The same ratio across a program

Some agencies publish the ratio as a program total. MassDOT’s retrospective on its state fiscal year 2026 highway capital plan, presented by Deputy Chief Engineer Jack Moran on September 9, 2026, compares total bid value with total estimate across its bid openings.

MassDOT highway bid openings, full program, by state fiscal year.
State fiscal yearBid openingsTotal bid valueTotal estimateBid as percent of estimate
2024197$1,288,441,976$1,224,750,099105%
2025188$2,189,465,454$2,074,909,454106%
2026185$1,141,195,921$1,178,513,50597%
Source: mass.gov

Bids ran 5% and 6% over estimate in fiscal 2024 and 2025 and 3% under in fiscal 2026. The same slide breaks out a smaller set it labels “Board Threshold,” with 14 openings in fiscal 2026 at 102% of estimate.

Worked example

The figures below are an example. A heavy civil contractor logs six public bids it submitted over a year. For each one, the chief estimator records the engineer’s estimate from the bid tab, the company’s bid, the low bid and the bidder count.

Example. Six public bids with round numbers. Percentages divide by the engineer's estimate or the low bid as labeled.
BidEngineer's estimateYour bidLow bidBiddersLow bid as % of estimateYour bid as % of estimateYour bid as % of low bid
1$2,000,000$1,900,000$1,900,000495.0%95.0%100.0% (won)
2$5,000,000$5,300,000$4,800,000696.0%106.0%110.4%
3$1,000,000$1,150,000$1,120,0003112.0%115.0%102.7%
4$8,000,000$7,600,000$7,600,000295.0%95.0%100.0% (won)
5$3,000,000$3,100,000$2,640,000788.0%103.3%117.4%
6$4,000,000$4,200,000$4,100,0005102.5%105.0%102.4%
Total$23,000,000$22,160,00096.3%

Read the log in this order:

  1. How the market priced the work. The low bid landed within 10% of the estimate on four of six jobs, bids 1, 2, 4 and 6. Bid 3 came in at 12% over and bid 5 at 12% under. In total, low bids came to $22,160,000 against $23,000,000 of estimates, or 96.3%.
  2. How the company priced the work. Its bids ran from 95.0% to 115.0% of the estimate. It won the two jobs where it bid 95.0%.
  3. How far off the losing bids were. On the four losses, the company averaged 108.2% of the low bid. Bids 3 and 6 missed by less than 3%. Bid 5 missed by 17.4% on a job that drew seven bidders.

Bid 5 is the one to review. Seven bidders and a low bid at 88% of the estimate point to heavy competition for that type of work. Bid 3 is the opposite case, with three bidders and a low bid 12% over the estimate.

Setting it up in Excel

Put one row per bid in a table, with the engineer’s estimate in C, your bid in D, the low bid in E and the bidder count in F.

  • Low bid variance: =(E2-C2)/C2
  • Your bid variance: =(D2-C2)/C2
  • Your bid against the low: =D2/E2-1
  • Within FHWA’s 10% band: =ABS(E2-C2)/C2<=0.1

Add columns for owner, work type, county and bid month. A pivot table on work type and bidder count then shows where low bids run under the estimate and where they run over.

How to use it on your jobs

The log adds price to the bid-hit ratio you may already track. A win rate tells you how often you won, and the variance shows how close the losses came. If your losing bids cluster a few percent above the low, check your markup against the markup-to-margin conversion before cutting cost.

FHWA’s guidance names inflation as one reason an agency may need to change how it estimates. When the low bid keeps landing over the estimate on one work type, compare the timing with the spread between building prices and input costs, and check whether your own estimates carry escalation to the midpoint of construction.

To start, pull the bid tabs for your last ten public bids from the owners’ websites. Enter the estimate, your bid, the low bid and the bidder count for each, and compute the variance against the estimate.