In late November the superintendent on a structural concrete job has to decide when to strip forms, pull shores and take the blankets off. Cylinders cured beside the pour are the usual guide, and in cold weather they can mislead. The maturity method estimates the strength of the concrete in the structure from its own temperature record. It is described in ASTM C1074, and the National Ready Mixed Concrete Association (NRMCA), the Federal Highway Administration (FHWA) and the Iowa Department of Transportation each publish a plain-language version of it.
What the method measures
Concrete gains strength as the cement hydrates, and temperature sets the pace. NRMCA’s CIP 39 gives an example: concrete cured at 50°F for 7 days may have the same maturity index as concrete cured at 80°F for 3 days, and the two would have similar strengths. The maturity index is a single number that combines time and temperature, and the method assumes that samples of the same mix with the same index have about the same strength.
NRMCA lists the jobsite decisions the method supports. They include form removal, reshoring, backfilling walls, scheduling post-tensioning, opening pavements and ending cold-weather protection. CIP 39 also explains why field-cured cylinders fall short. A cylinder is much smaller than the element it represents, so it does not follow the same temperature history.
The formula
The version state highway agencies use most is the Nurse-Saul function. It adds up the concrete temperature above a floor, hour by hour. The result is the temperature-time factor (TTF), in degree-hours.
Iowa DOT’s IM 383 writes it as M = Σ(T − T0)Δt. T is the average concrete temperature during an interval, Δt is the length of the interval in hours, and T0 is the datum temperature, the point below which the concrete is assumed to stop gaining strength. FHWA’s TechBrief says hours at or below the datum add nothing.
In a spreadsheet with hours in column A, the average temperature in °C in column C and the datum in a cell named Datum, the steps are:
- In each row, compute the interval:
=MAX(0, C2 - Datum) * (A2 - A1). The MAX keeps cold hours below the datum from subtracting. - Keep a running total:
=SUM($D$2:D2). - Read the strength off the mix’s calibration curve at the running total.
The calibration curve comes first. The contractor or the supplier casts cylinders from the project mix, embeds a temperature sensor in one or two of them, and breaks the rest at set ages. FHWA’s TechBrief says 12 to 15 specimens is typical, tested at 1, 3, 7, 14 and 28 days. Each break gives one pair of TTF and strength. Iowa DOT requires a minimum of 17 cylinders for structural concrete of 4,500 psi or more, with probes in two of them.
A worked example
The example below uses round numbers and a hypothetical mix. A contractor places an elevated slab in late November under insulated blankets. The engineer of record has set 3,000 psi as the strength needed before forms come off. A logger records the concrete temperature every hour, and the table averages it over 12-hour blocks to fit the page. Iowa DOT bases structural maturity values on hourly readings, and the spreadsheet steps are the same with one row per hour.
The datum here is -10°C (14°F), the value FHWA says is generally used and Iowa DOT says is most commonly used.
| Cylinder age (days) | Lab TTF (C-hours) | Average compressive strength (psi) |
|---|---|---|
| 1 | 792 | 1,500 |
| 3 | 2,376 | 2,900 |
| 7 | 5,544 | 3,900 |
| 14 | 11,088 | 4,500 |
| 28 | 22,176 | 5,000 |
On this curve, 3,000 psi falls between the 3-day and 7-day breaks. Interpolating between them puts the target at 2,693 °C-hours. The lab cylinders reach that in about 82 hours.
The example slab passes the 2,693 °C-hour target at about hour 148
Cumulative temperature-time factor, °C-hours above a -10°C datum, by hours after placement. Example calculation.
| Hours after placement | Average concrete temperature (F) | Average concrete temperature (C) | Interval TTF (C-hours) | Cumulative TTF (C-hours) |
|---|---|---|---|---|
| 12 | 61 | 16 | 312 | 312 |
| 24 | 59 | 15 | 300 | 612 |
| 36 | 52 | 11 | 252 | 864 |
| 48 | 48 | 9 | 228 | 1,092 |
| 60 | 46 | 8 | 216 | 1,308 |
| 72 | 45 | 7 | 204 | 1,512 |
| 84 | 45 | 7 | 204 | 1,716 |
| 96 | 43 | 6 | 192 | 1,908 |
| 108 | 43 | 6 | 192 | 2,100 |
| 120 | 41 | 5 | 180 | 2,280 |
| 132 | 41 | 5 | 180 | 2,460 |
| 144 | 41 | 5 | 180 | 2,640 |
| 156 | 41 | 5 | 180 | 2,820 |
The slab reaches 2,640 °C-hours at hour 144 and gains 15 °C-hours an hour after that, so it crosses the target at about hour 148, a little over six days after placement.
At hour 84, when cylinders held at lab temperature would have passed 3,000 psi, the slab is at 1,716 °C-hours. The curve reads that as about 2,300 psi. A crew that stripped on the lab schedule would pull forms from concrete about 700 psi short of the engineer’s number.
The datum temperature
The sources do not use the same datum. NRMCA suggests 0°C for Type I portland cement when the concrete will stay between 0 and 40°C, and it says ASTM C1074 gives guidance for choosing the value for a particular mix. FHWA and Iowa DOT use -10°C.
The choice matters most in cold weather, because cold hours carry little weight at a 0°C datum. The table reruns the example with a 0°C datum applied to both the lab cylinders and the slab.
| Datum temperature (C) | TTF for 3000 psi from the lab curve (C-hours) | Field TTF at hour 156 (C-hours) | Hours for the pour to reach 3000 psi |
|---|---|---|---|
| -10 | 2,693 | 2,820 | 148 |
| 0 | 1,877 | 1,260 | 279 |
At a 0°C datum the slab needs about 279 hours, close to 12 days. NRMCA treats the strength-maturity relationship, the datum and the activation energy as specific to each mix, so the datum belongs with the calibration curve and is set before the first pour. Iowa DOT’s procedure tells technicians to check that each maturity meter is set to -10°C before use.
Limits of the method
NRMCA lists four ways the estimate goes wrong. The delivered concrete may differ from the calibration batch in cementitious materials, admixtures, batching or air content. The placement temperature can change the rate of strength gain. Poor placement, consolidation or curing can stop hydration. The datum or activation energy may not fit the mix.
For those reasons, NRMCA says ASTM C1074 suggests supplementary tests before safety-critical operations such as form removal or post-tensioning. CIP 39 names penetration resistance (ASTM C803), cast-in-place cylinders (ASTM C873) and pullout strength (ASTM C900). NRMCA also says maturity estimates do not replace standard-cured cylinders for quality assurance.
FHWA adds that the method is meant for early ages, generally under 14 days, and that a change in the mix design calls for a new curve. Iowa DOT requires a curve validation every 90 calendar days and a new curve when production water-cement ratio runs more than 0.02 above the calibration batch.
How to use it on your jobs
The number to track is hours from placement to the stripping strength, by element and by month. Pull it from the logger record for every pour this winter and set it beside the stripping dates the schedule assumed. The gap tells the scheduler how many days of form cycle to carry in cold months, and it feeds the same winter planning as the temporary heat budget and the working-day calendar.
Probe placement decides what the number means. Iowa DOT requires at least two probes on structures, tied to the reinforcing steel near the edge at the upper corner of the exposed surface.
To start, ask the ready-mix supplier whether a maturity curve already exists for the mix on your next elevated pour and which datum it used. If one does, put a logger in that pour and run the three spreadsheet steps alongside the field-cured cylinders.