Pulley, a San Francisco company that manages commercial building permits, announced $64 million in funding on November 18, 2026. The total combines a $41 million Series B led by Jump Capital and a $23 million Series A led by CRV and Susa Ventures. Pulley’s service pairs licensed permitting staff with AI agents, software that carries out a multi-step task on its own, and the company says the money will pay for AI drawing review that flags building code issues during design. That work sits in the permit set an owner and its design team assemble before mobilization, and in the comment-and-resubmit loop that follows.
What it does
Pulley lays out the service in the order a permit moves. It starts with due diligence and a permit plan that lists the approvals a project needs and forecast approval dates. Before submission, Pulley’s AI agents and staff review the drawings and application documents. After filing, its team talks with plan reviewers, works out comment responses with the project’s architects and engineers, and tracks status across jurisdictions in a dashboard.
By Pulley’s own description, its staff does most of the work. The company says a team of more than 75 licensed architects, former plan reviewers and city planners handles applications, and its FAQ describes the offering as a managed service supported by software, which the customer does not run itself. The company also says it is certified to approve plans in place of the local building department through private plan review programs covering more than 2,000 cities and counties.
The buyers are owners running many similar projects. The release names Amazon, Starbucks, JLL and Equinix, and the FAQ says Pulley suits organizations with 20 or more projects a year. A GC on a national store rollout or a tenant-improvement program would work beside Pulley as the owner’s permitting partner, with Pulley’s forecast approval dates feeding the mobilization schedule. (Suffolk, the general contractor, is on Pulley’s list of investors.)
The drawing review is new. The release gives it one sentence, saying it will find code compliance issues earlier in design to cut redesign and speed approvals. Its release date and the codes it covers are not in the announcement.
Evidence so far
The evidence is Pulley’s release and blog post, its website, a Hibbett Sports case study published on Pulley’s site, and one comment from a Meta design and delivery manager in the release. These figures come from Pulley:
| Figure | Value | Reported by |
|---|---|---|
| Project time saved for customers | 11,750 weeks | Pulley release and website |
| Value of commercial projects supported | $21 billion | Pulley release and website |
| Faster permit approvals | Up to 70% | Pulley release and website |
| Rounds of jurisdiction comments per project | About one on average (1.1 in the website FAQ) | Pulley release and website |
| Projects approved with no comments | More than 40% (about 40% in the FAQ) | Pulley release and website |
| Review comments this year compared with 2025 | 65% fewer | Pulley release |
| Hibbett permit time in Jacksonville | More than 140 days before Pulley and 30 days with it | Hibbett case study on Pulley's site |
| Hibbett estimated added revenue from opening four weeks before Black Friday | $385,000 | Hibbett case study on Pulley's site |
The 11,750 weeks saved across $21 billion of projects depends on what Pulley compares each project against, and the project count and that baseline method are not in the sources. “Up to 70%” marks the top of the range customers saw.
The comment figures are closer to what a building department records. An average of about one comment round, with roughly 40% of projects approved on first submission, can be checked against your own permit history. The 65% drop in review comments compares this year’s projects with 2025’s, so a shift toward easier jurisdictions or simpler scopes would also lower the count. The release attributes the drop to a system that learns from each project.
The Hibbett case study gives the clearest before-and-after. Hibbett started with about eight stores. In Jacksonville, where permits had taken Hibbett more than 140 days, Pulley got one in 30. That works out to a cut of about 79%, which the case study rounds to 80%. Pulley credits the result to a pre-submission meeting with the city and advice from the city’s former planning director, so the Jacksonville result shows what the expert side of the service did. It says little about the AI side. So for a contractor, the useful reading is narrow. Pulley reports fewer review cycles on commercial permits it manages. How much of that comes from the AI agents and how much from the 75 experts is not broken out.
How to measure it on your projects
Track comment rounds per permit: the number of times a building department sends back comments before it issues the permit. Pulley’s FAQ notes that each avoidable resubmission can trigger another review cycle and add weeks. Pair it with calendar days from first submission to issuance, by jurisdiction.
| Metric | Definition | Baseline to capture before the pilot |
|---|---|---|
| Comment rounds per permit | Number of times the building department returned comments before it issued the permit | Count from the permit records of your last 10 to 20 similar jobs |
| Share approved with no comments | Permits issued on the first submission divided by permits submitted | Same set of past permits |
| Submission to issuance | Calendar days from first submission to permit issuance | Same set of past permits grouped by jurisdiction |
| Forecast error | Actual issuance date minus the date forecast at submission in calendar days | The issuance date your schedule assumed on each past job |
Your baseline already exists in past permit files:
- Pull the permit records for your last 10 to 20 jobs of a similar type.
- For each, record the submission date, every comment letter, and the issuance date.
- Group the results by jurisdiction, since each building department runs its own review queue.
- Note the issuance date your schedule assumed at submission, and compute the gap.
If an owner brings in Pulley, compare its jobs with this baseline in the same jurisdictions. To turn the day counts into working days for a schedule, use the method in counting working days over the holidays. For other AI permit-review tools, see the posts on Denver’s CivCheck intake check and UpCodes plan review.
Availability and cost
Pulley prices by quote, based on project scope, permitting requirements and project count. The FAQ says it works in all 50 states, has permitted projects in about 2,000 jurisdictions, and connects to about 20,000 jurisdiction portals to track requirements and status. It handles site permits, building permits, health department reviews and trade permits. Entitlements generally fall outside its core service, though it takes on limited discretionary approvals, such as conditional use permits, for an additional fee. The drawing review and the site selection tools are described as coming products.