Pulley, a San Francisco company that manages commercial building permits, announced $64 million in funding on November 18, 2026. The total combines a $41 million Series B led by Jump Capital and a $23 million Series A led by CRV and Susa Ventures. Pulley’s service pairs licensed permitting staff with AI agents, software that carries out a multi-step task on its own, and the company says the money will pay for AI drawing review that flags building code issues during design. That work sits in the permit set an owner and its design team assemble before mobilization, and in the comment-and-resubmit loop that follows.

What it does

Pulley lays out the service in the order a permit moves. It starts with due diligence and a permit plan that lists the approvals a project needs and forecast approval dates. Before submission, Pulley’s AI agents and staff review the drawings and application documents. After filing, its team talks with plan reviewers, works out comment responses with the project’s architects and engineers, and tracks status across jurisdictions in a dashboard.

By Pulley’s own description, its staff does most of the work. The company says a team of more than 75 licensed architects, former plan reviewers and city planners handles applications, and its FAQ describes the offering as a managed service supported by software, which the customer does not run itself. The company also says it is certified to approve plans in place of the local building department through private plan review programs covering more than 2,000 cities and counties.

The buyers are owners running many similar projects. The release names Amazon, Starbucks, JLL and Equinix, and the FAQ says Pulley suits organizations with 20 or more projects a year. A GC on a national store rollout or a tenant-improvement program would work beside Pulley as the owner’s permitting partner, with Pulley’s forecast approval dates feeding the mobilization schedule. (Suffolk, the general contractor, is on Pulley’s list of investors.)

The drawing review is new. The release gives it one sentence, saying it will find code compliance issues earlier in design to cut redesign and speed approvals. Its release date and the codes it covers are not in the announcement.

Evidence so far

The evidence is Pulley’s release and blog post, its website, a Hibbett Sports case study published on Pulley’s site, and one comment from a Meta design and delivery manager in the release. These figures come from Pulley:

Figures Pulley and its customer report
FigureValueReported by
Project time saved for customers11,750 weeksPulley release and website
Value of commercial projects supported$21 billionPulley release and website
Faster permit approvalsUp to 70%Pulley release and website
Rounds of jurisdiction comments per projectAbout one on average (1.1 in the website FAQ)Pulley release and website
Projects approved with no commentsMore than 40% (about 40% in the FAQ)Pulley release and website
Review comments this year compared with 202565% fewerPulley release
Hibbett permit time in JacksonvilleMore than 140 days before Pulley and 30 days with itHibbett case study on Pulley's site
Hibbett estimated added revenue from opening four weeks before Black Friday$385,000Hibbett case study on Pulley's site
Source: businesswire.com

The 11,750 weeks saved across $21 billion of projects depends on what Pulley compares each project against, and the project count and that baseline method are not in the sources. “Up to 70%” marks the top of the range customers saw.

The comment figures are closer to what a building department records. An average of about one comment round, with roughly 40% of projects approved on first submission, can be checked against your own permit history. The 65% drop in review comments compares this year’s projects with 2025’s, so a shift toward easier jurisdictions or simpler scopes would also lower the count. The release attributes the drop to a system that learns from each project.

The Hibbett case study gives the clearest before-and-after. Hibbett started with about eight stores. In Jacksonville, where permits had taken Hibbett more than 140 days, Pulley got one in 30. That works out to a cut of about 79%, which the case study rounds to 80%. Pulley credits the result to a pre-submission meeting with the city and advice from the city’s former planning director, so the Jacksonville result shows what the expert side of the service did. It says little about the AI side. So for a contractor, the useful reading is narrow. Pulley reports fewer review cycles on commercial permits it manages. How much of that comes from the AI agents and how much from the 75 experts is not broken out.

How to measure it on your projects

Track comment rounds per permit: the number of times a building department sends back comments before it issues the permit. Pulley’s FAQ notes that each avoidable resubmission can trigger another review cycle and add weeks. Pair it with calendar days from first submission to issuance, by jurisdiction.

Metrics to capture before a permitting pilot
MetricDefinitionBaseline to capture before the pilot
Comment rounds per permitNumber of times the building department returned comments before it issued the permitCount from the permit records of your last 10 to 20 similar jobs
Share approved with no commentsPermits issued on the first submission divided by permits submittedSame set of past permits
Submission to issuanceCalendar days from first submission to permit issuanceSame set of past permits grouped by jurisdiction
Forecast errorActual issuance date minus the date forecast at submission in calendar daysThe issuance date your schedule assumed on each past job

Your baseline already exists in past permit files:

  1. Pull the permit records for your last 10 to 20 jobs of a similar type.
  2. For each, record the submission date, every comment letter, and the issuance date.
  3. Group the results by jurisdiction, since each building department runs its own review queue.
  4. Note the issuance date your schedule assumed at submission, and compute the gap.

If an owner brings in Pulley, compare its jobs with this baseline in the same jurisdictions. To turn the day counts into working days for a schedule, use the method in counting working days over the holidays. For other AI permit-review tools, see the posts on Denver’s CivCheck intake check and UpCodes plan review.

Availability and cost

Pulley prices by quote, based on project scope, permitting requirements and project count. The FAQ says it works in all 50 states, has permitted projects in about 2,000 jurisdictions, and connects to about 20,000 jurisdiction portals to track requirements and status. It handles site permits, building permits, health department reviews and trade permits. Entitlements generally fall outside its core service, though it takes on limited discretionary approvals, such as conditional use permits, for an additional fee. The drawing review and the site selection tools are described as coming products.