Oracle announced three additions to Oracle Primavera Cloud on November 18, 2026: an updated pull planning experience, a workspace-level risk library, and an AI help assistant. The pull planning update affects the superintendent and trade foremen who sequence a phase and carry it into the weekly work plan. Project managers who start each job’s risk register get the library, and the assistant answers questions about using the software itself.
What it does
Many teams run pull planning with sticky notes on a wall, and someone in the project engineer’s seat types the result into a look-ahead afterward. Oracle describes the new feature as a way to turn that sticky-note exercise into a connected digital workflow, and its 26.11 release notes lay out the steps.
The team picks a finish milestone or activity and plans backward. Each task gets a duration, a crew size and its hand-offs to the next trade, with no calendar dates assigned while the sequence is still being worked out.
The work happens on a Planning Board, with a Parking Lot for tasks not yet placed in the sequence. Participants in a live session see each other’s changes as they make them. A pull plan moves through three statuses:
- In Planning, when users with the right privileges can add, move and delete tasks and hand-offs.
- Approved, when the board becomes read-only. An authorized user can withdraw approval to reopen it.
- Released to Work Plan, when the tasks appear on the Work Plan for lookahead planning and weekly and daily huddles.
Oracle’s announcement gives the example of sequencing framing, mechanical, electrical and plumbing work, plus the inspections required before drywall. The field tasks stay tied to the CPM contract schedule, so the scheduler and the superintendent work from the same plan. Oracle’s product page says the system calculates planned percent complete and logs missed commitments for its dashboards.
The risk library is a shared list of reusable risks for a whole workspace, such as material price changes, supply chain delays, skilled labor shortages or adverse weather. A project team adds risks from the library to its own register, links existing project risks to library entries, and proposes new ones.
An approver accepts or rejects each proposed risk, according to the help documentation. The 26.11 release adds reports, charts and dashboards built from library risks and the project risks linked to them, so a risk manager can see which risks recur across jobs.
The help assistant is the generative AI piece. It answers questions in plain language, such as “How do I add a baseline?”, from two sources only: Primavera Cloud’s help documentation and its REST API documentation. Oracle’s help page says it is not designed to give deployment advice, synthesize customer data or generate new content. Each user can send up to 100 messages a day.
Evidence so far
The evidence is Oracle’s November 18 announcement, its 26.11 release notes and its help documentation. These claims come from Oracle:
- The help assistant can reduce time spent searching documentation and the need for support on common questions.
- The risk library reduces repeated data entry and makes risk identification more consistent across projects.
- The pull planning workflow helps owners, general contractors and subcontractors agree on the tasks, sequence and responsibilities needed to reach a milestone.
Oracle’s own help page adds a caution about the assistant. Its answers may be out of date, inaccurate or incomplete, and users should check them against trusted sources.
Results from field use, such as changes in plan reliability or milestone dates, are not yet public.
How to measure it on your projects
The metric that fits pull planning is Percent Plan Complete, or PPC. It is the number of committed tasks finished in the week they were promised, divided by the number committed that week. For this test, count only tasks released from a pull plan, and pair PPC with milestone variance, the calendar days between the pull plan’s target milestone and the actual finish.
Capture the baseline before the first digital pull plan. Use PPC from your look-ahead sheets and the planned and actual dates for a few recent milestones of the same type, such as dry-in or start of drywall on a floor. If your team will also use the risk library, count the risks on the last comparable job that cost money or time but were never in the register.
| Metric | Definition | Baseline to capture before the pilot |
|---|---|---|
| Milestone PPC | Tasks released from the pull plan and finished in the week committed divided by tasks committed that week | Weekly PPC for the same phase on the last comparable job or the last 8 weeks of look-ahead sheets |
| Milestone variance | Calendar days between the pull plan's target milestone and the actual finish | Planned and actual dates for 3 to 5 recent milestones of the same type |
| Missed commitment reasons | Count of missed tasks by reason code such as RFI or submittal or manpower or weather | Last 8 weeks from look-ahead notes and daily reports |
| Risks that hit unregistered | Risks that affected cost or schedule but were not in the register at the start of the phase | Count from change orders and delay notices on the last comparable job |
Our post on Trimble Connect Scheduling uses the same PPC baseline for a competing product. To check whether released pull plans protect the contract schedule, track float with the method in tracking total float across schedule updates.
Start with one phase on one job, such as the MEP rough-in on a single floor. Pull its last eight weekly look-aheads and compute PPC for each week before the trades meet at the Planning Board.
Availability and cost
Oracle says the help assistant, the risk library and the updated pull planning are generally available now. The assistant is off by default, and an application administrator has to turn it on. Oracle’s availability page lists it in the North America data centers coded PHX and IAD, the Middle East and Africa data center JED, and the Europe data center FRA. Oracle prices Primavera Cloud through its sales team.