ABC / Construction Backlog Indicator / October 2026 Survey Oct 20 to Nov 3 · released Nov 10

Backlog · Nonresidential construction · Data centers

ABC’s Construction Backlog Indicator fell to 8.1 months in October as backlog for contractors without data center work dropped to 7.6

Backlog slipped 0.6 months in October, the largest drop since July. This month ABC split the figure by data center work, and the split shows where the drop came from: the 88% of contractors with no data center contracts fell to 7.6 months, while those with data center work rose to 11.5.

Backlog, October 2026
8.1months
From September
−0.6September: 8.7, not revised
From October 2025
−0.3October 2025: 8.4
Lower readings in 25 months
2January and July 2026, both 8.0
Contractors without data center work carry 3.9 fewer months of backlog than those with it
0m1m2m3m4m5m6m7m8m9m10m11m12mWith data center work11.5+0.2Without data center work88% of contractors7.6−0.73.9 months apartAll contractors 8.1Dashed outline: September 2026 0m2m4m6m8m10m12mWith data center work11.5+0.2Without data center work (88%)7.6−0.73.9 months apartAll contractors 8.1Dashed outline: September 2026

Construction Backlog Indicator, months of work under contract as a share of prior-year revenue, ABC member survey, October 2026 against September 2026. Bars are October. Green rose from September, red fell. The data center split appears in the release text only. Source: Associated Builders and Contractors, November 10 release

Associated Builders and Contractors reported on November 10 that its Construction Backlog Indicator fell to 8.1 months in October 2026. That is 0.6 months below September’s 8.7 and 0.3 months below October 2025. The indicator measures work under contract but not yet performed, expressed as months of a firm’s prior-year revenue, and it comes from a survey of ABC member firms in commercial, industrial and infrastructure construction. ABC ran the October survey from October 20 to November 3.

The 0.6-month drop is the largest since July, when the reading fell 0.8. Over the past 12 months the indicator has averaged 8.4 months, and in the last 25 months only January and July 2026, both at 8.0, came in lower.

The national series

Backlog fell to 8.1 months after two monthly gains

7.58.08.59.09.5Oct 2024Apr 2025Oct 2025Apr 2026Oct 202612-monthaverage 8.4Jan 8.0Jul 8.0, down 0.8May 9.1Oct 8.1 7.58.08.59.09.5Oct 2024Oct 2025Oct 2026Jul 8.0May 9.18.1

ABC Construction Backlog Indicator, months of work under contract, October 2024 to October 2026. The scale starts at 7.5 months. Each dot is colored by its change from the month before: green rose, red fell, gray unchanged. The dashed line is the average of the last 12 months, 8.4. Member survey. ABC’s methodology note does not describe a seasonal adjustment. Source: ABC CCI and CBI time series, November 4, 2026 workbook

What moved

The 88% of contractors with no data center work fell to 7.6 months from 8.3

This month ABC split the national figure by whether a contractor has data center work. ABC chief economist Anirban Basu said the decline came mostly from the 88% of contractors with no data center contracts, whose backlog fell to 7.6 months from 8.3. Contractors with data center work rose to 11.5 months from 11.3, and Basu said most of them have more than $100 million in annual revenue.

“Backlog fell sharply in October, returning to levels not consistently observed since last winter.”

Anirban Basu, chief economist, Associated Builders and Contractors

On average, then, members without a data center job carry 3.9 fewer months of work than members with one.

Segments, regions and firm size

Heavy industrial rose 2.0 months to 10.1 while commercial and institutional fell a full month to 8.0

The segment rows in ABC’s workbook show where the drop landed. Commercial and institutional backlog fell a full month to 8.0, tying July for the segment’s lowest reading of 2026. ABC’s methodology note puts data centers in that segment, along with offices, schools, hospitals, multifamily and warehouses. Infrastructure fell to 8.7 months, which ABC says is the lowest since May 2025. Heavy industrial went the other way, rising 2.0 months to 10.1, a 15-month high by ABC’s count.

0m1m2m3m4m5m6m7m8m9m10m11m12mAll contractors 8.1MARKET SEGMENTHeavy industrial10.1+2.0Infrastructure8.7−0.7Commercial and institutional8.0−1.0REGIONSouth10.1−0.2Middle States7.8+1.1Northeast7.5−1.0West6.6−1.5FIRM REVENUEUnder $30 million7.1−0.6$30 million to $50 million9.2+2.8$50 million to $100 million9.2−2.1$100 million or more11.6−0.2OCTVS SEP 0m2m4m6m8m10m12mAll contractors 8.1MARKET SEGMENTHeavy industrial10.1+2.0Infrastructure8.7−0.7Commercial and institutional8.0−1.0REGIONSouth10.1−0.2Middle States7.8+1.1Northeast7.5−1.0West6.6−1.5FIRM REVENUEUnder $30 million7.1−0.6$30 million to $50 million9.2+2.8$50 million to $100 million9.2−2.1$100 million or more11.6−0.2

Backlog in months by segment, region and firm revenue, October 2026, with September 2026 as the dashed outline. Segments and regions are sorted by October backlog, revenue bands by size. All rows share one scale. Subgroups rest on fewer responses than the national figure. Source: ABC CCI and CBI time series, November 4, 2026 workbook

Three of the four regions fell. The West dropped 1.5 months to 6.6, matching February for its lowest reading this year, and the Northeast fell to 7.5 from 8.5. The South slipped 0.2 months to 10.1, still the highest of the four. The Middle States, ABC’s 12-state block from Ohio and Michigan west to the Dakotas and Kansas, recovered to 7.8 after September’s 6.7.

The revenue bands moved in large, opposite steps. The $50 million to $100 million band fell 2.1 months to 9.2, and the $30 million to $50 million band rose 2.8 months to the same 9.2, undoing most of its September drop. The $100 million-plus band slipped to 11.6 from 11.8.

That last figure sits a little oddly next to Basu’s account, since he describes the data center group as mostly large firms and that group gained. Both can hold if large firms without data center work lost enough backlog to offset the gain. The release does not break the top revenue band down further, so the data cannot settle it.

Confidence

Margin expectations rose to 53.3 while sales and staffing slipped

The Construction Confidence Index comes from the same survey. It is a diffusion index, meaning a reading above 50 says more firms expect growth than decline over the next six months. Profit margins rose to 53.3 from 52.0, the highest since March. Sales fell to 59.9 from 60.1 and staffing to 59.4 from 60.7, both the lowest since November 2025.

SALES59.9, from 60.15055606570202420252026PROFIT MARGINS53.3, from 52.05055606570202420252026STAFFING59.4, from 60.75055606570202420252026 SALES59.9, from 60.15055606570202420252026PROFIT MARGINS53.3, from 52.05055606570202420252026STAFFING59.4, from 60.75055606570202420252026

ABC Construction Confidence Index, six-month outlook, October 2024 to October 2026, all three panels on one scale. The heavier line is 50, where as many firms expect a decline as a rise. Source: ABC CCI and CBI time series, November 4, 2026 workbook

Expectations

23.6% of contractors expect profit margins to shrink over the next six months

Basu called the margin reading encouraging given recent increases in materials prices and borrowing costs, and added that roughly 1 in 4 contractors still expect margins to shrink. In the workbook that share is 23.6%, with 20.0% expecting margins to fall a little and 3.6% a lot. On sales, 5.1% of respondents expect a large decline over the next six months, the highest share since June 2023.

  • Down a lot
  • Down a little
  • No change
  • Up a little
  • Up a lot
Sales5.1%15.4%23.1%47.7%8.7%Profit margins3.6%20.0%40.5%31.3%4.6%Staffing levels1.0%11.3%41.0%42.6%4.1% Sales5.1%15.4%23.1%47.7%8.7%Profit margins3.6%20.0%40.5%31.3%4.6%Staffing levels1.0%11.3%41.0%42.6%4.1%

Share of respondents by expected change over the next six months, October 2026 survey. Source: ABC CCI and CBI time series, November 4, 2026 workbook

How to use this number

A firm with $36 million of signed work on $60 million of revenue carries 7.2 months

ABC computes each firm’s figure as current backlog dollars divided by prior fiscal-year revenue, times 12. You can run the same arithmetic on your own books:

  1. Take signed backlog from your work-in-progress schedule at the end of October.
  2. Divide by last fiscal year’s revenue and multiply by 12.
  3. Compare the result with the national 8.1, the 7.6 for contractors without data center work, and the rows in the segment table that match your market, region and size.
fx=36/60*127.2

As an example with round numbers, a firm with $60 million in prior-year revenue and $36 million of signed, unbilled work has 36 divided by 60, times 12, or 7.2 months. That is 0.9 months below the national figure but only 0.4 months below members without data center work. If the firm has no data center contracts, the 7.6 is the closer benchmark. The site’s post on computing backlog in months walks through the calculation in more detail.

The example firm sits 0.4 months below contractors without data center work
0m1m2m3m4m5m6m7m8m9m10m11m12mExample firm7.2Without data center work7.6All contractors8.10.4 months to 7.60.9 months to 8.1 0m2m4m6m8m10m12mExample firm7.2Without data center work7.6All contractors8.10.4 months to 7.60.9 months to 8.1

Months of backlog. The example firm uses round numbers from the article. The benchmarks are ABC’s October 2026 figures. Source: Associated Builders and Contractors

The second use is tracking the split over time. The data center figures appear in the release text and are not a column in ABC’s workbook, so you would need to record them from each monthly release. Put your own monthly figure next to the no-data-center line in the same sheet or Power BI table you use for WIP. A gap between the two that persists for several months is a reason to check your own pipeline, starting with bid volume and hit rate.

Revisions and caveats

September’s 8.7 carried into the November 4 workbook unrevised

September’s 8.7 was not revised. ABC reported 8.7 in its October 13 release, and the November 4 workbook carries the same figure. The workbook replaces the full history each month, so earlier months could change without a mention in the release text.

The indicator is a member survey, and the number of responding firms is not in the release or the methodology note. Subgroups such as a single region or revenue band rest on fewer responses than the national figure, which may explain one-month swings like the 2.8-month rise in the $30 million to $50 million band. The data center split also appears only in the release text, so its history cannot be checked against the workbook. In September Basu put the share of members with data center work at 15%. The October release’s 88% without it implies about 12%, and neither release says whether the difference comes from the sample or from firms finishing or starting data center jobs.

ABC’s methodology note says the backlog figure covers the previous month’s work under contract, based on the latest financials each firm has. ABC revised the reference months for the whole series in May 2020 to better match the survey period. The note does not describe a seasonal adjustment. (Last year the indicator also slipped in October and fell again in November.) The year-over-year comparison avoids that issue, and on that basis backlog is down 0.3 months.

The data

Backlog fell 0.6 months in October, the largest drop since July’s 0.8

National backlog, months
MonthBacklogPrior monthYear earlier
Oct 20258.4−0.10.0
Nov 20258.1−0.3−0.3
Dec 20258.2+0.1−0.1
Jan 20268.0−0.2−0.4
Feb 20268.1+0.1−0.2
Mar 20268.6+0.5+0.1
Apr 20268.8+0.2+0.1
May 20269.1+0.3+0.7
Jun 20268.8−0.3+0.1
Jul 20268.0−0.8−0.8
Aug 20268.5+0.50.0
Sep 20268.7+0.2+0.2
Oct 20268.1−0.6−0.3
By segment, region and revenue, months
GroupOct 2025Sep 2026Oct 2026From SepFrom Oct 2025
Market segment
Commercial and institutional8.59.08.0−1.0−0.5
Heavy industrial8.88.110.1+2.0+1.3
Infrastructure9.89.48.7−0.7−1.1
Region
Middle States8.16.77.8+1.1−0.3
Northeast7.78.57.5−1.0−0.2
South9.610.310.1−0.2+0.5
West8.18.16.6−1.5−1.5
Firm revenue
Under $30 million7.37.77.1−0.6−0.2
$30 million to $50 million9.46.49.2+2.8−0.2
$50 million to $100 million10.411.39.2−2.1−1.2
$100 million or more12.211.811.6−0.2−0.6

Download the data: table.csv, segments.csv. Data center split: datacenter.csv. Confidence index: confidence.csv. Expectations: expectations.csv. 25-month series: data.csv. Source: ABC CCI and CBI time series, November 4, 2026 workbook